Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
47W442 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1338/।।।(2)/21-10(एम.एल.ए.)/ 2017 टी.सी-।।।. दि0 11.05.2021
TS Amount (lakhs) : 113.28 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
113.28
Resanction Cost :
113.28
Tentative Cost :
113.28
Exp. Upto Last Fy : 103.49
For CFY 2024-2025
Remaining : 9.79
Demand : 9.78
Allotment : 6.00
Exp in CFY : 9.16
Total Up to Date Exp : 112.65
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 2 months ago
11 May 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। -- as on 15-Jul-2024