Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 1.000 | 0.000 |
47W443 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1335(1)/।।।(2)/21-10(एम.एल.ए.)/ 2017 टी.सी. दि0 11.05.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
128.17
Resanction Cost :
128.17
Tentative Cost :
128.17
Exp. Upto Last Fy : 109.45
For CFY 2024-2025
Remaining : 18.72
Demand : 12.21
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 109.45
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
3 years 2 months ago
11 May 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मार्ग 4.00 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण। कि0मी0 5 में एच0पी0 बैण्ड़ पर ग्रामीणों द्वारा विवाद ग्रामीणों के साथ बैठक की जा रही है। -- as on 15-Jul-2024
Physical Peramenters