Work Profile Report [47W451]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : 2570/III(2)/21-10(MLA)/2017 Dt. 05.09.2021
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
76.56
Resanction Cost :
76.56
Tentative Cost :
76.56
Exp. Upto Last Fy :
19.58
For CFY 2025-2026
Remaining :
56.98
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
19.58
Survey work done
Sanction on : 3 years 10 months ago
05 Sep 2021
Physical Progress:
At start of FY 2025-2026 :
30 %
Up to Date :
30 %
Tentative Completion date on : 5 months 2 weeks from now
31 Dec 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ई0डी0पी0आर0 गठित की जा रही है । -- as on 04-Jun-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: