Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 130 | 130 | 130 | 0 |
47W451 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2570/III(2)/21-10(MLA)/2017 Dt. 05.09.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
76.56
Resanction Cost :
76.56
Tentative Cost :
76.56
Exp. Upto Last Fy : 19.58
For CFY 2024-2025
Remaining : 56.98
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 19.58
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 10 months ago
05 Sep 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0पी0आर0 स्वीकृति हेतु उच्चाधिकारियों को प्रेषित की गई है। -- as on 12-Feb-2024
Physical Peramenters