Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
47W458 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4987(1)/III(2)/21-10(MLA)/2017 TC Dt. 22.10.2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 53.35 Lacs
Resanction Cost : 53.35 Lacs
Exp. Upto Last Fy : 2.69 Lacs
For CFY 2024-2025
Remaining : 50.66 Lacs
Demand : 3.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 2.69 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 6 months ago
22 Oct 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रारम्भिक सर्वेक्षण की कार्यवाही पूर्ण। वर्तमान में समरेखण गठन की कार्यवाही की जा रही है। -- as on 09-Jan-2023
Physical Peramenters