Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
47W474 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2620(1)/III(2)/21-10(MLA)/2017 Dt. 10.08.2021
TS Amount (lakhs) : 132.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
132.31
Resanction Cost :
132.31
Tentative Cost :
132.31
Exp. Upto Last Fy : 115.93
For CFY 2024-2025
Remaining : 16.38
Demand : 16.38
Allotment : 10.00
Exp in CFY : 6.74
Total Up to Date Exp : 122.67
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
10 Aug 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। -- as on 13-Feb-2024
Physical Peramenters