Work Profile Report [47W476]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : 2620(1)/III(2)/21-10(MLA)/2017 Dt. 10.08.2021
TS Amount (lakhs) : 136.05 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
136.05
Resanction Cost :
136.05
Tentative Cost :
136.05
Exp. Upto Last Fy :
129.45
For CFY 2024-2025
Remaining :
6.60
Demand :
6.60
Allotment :
6.60
Exp in CFY :
6.84
Total Up to Date Exp :
136.28
Construction Started
Sanction on : 3 years 3 months ago
10 Aug 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
60 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
वित्तीय वर्ष के लक्ष्य 3.15 किमी0 के सापेक्ष 2.50 किमी0 पहाड कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand