Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.72 | 4.72 | 4.72 | 0 |
47W478 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4955(1)/III(2)/21-10(MLA)/2017 TC-III Dt. 14.10.2021
TS Amount (lakhs) : 82.33 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
91.93
Resanction Cost :
91.93
Tentative Cost :
91.93
Exp. Upto Last Fy : 84.73
For CFY 2024-2025
Remaining : 7.20
Demand : 7.19
Allotment : 2.00
Exp in CFY : 0.00
Total Up to Date Exp : 84.73
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
14 Oct 2021
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
1 year 4 months ago
28 Feb 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 14-Jul-2024
Physical Peramenters