Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 70 | 70 | 0.000 | 70 | 70.000 | 0.000 |
47W533 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 -470/।।।(2)/22-10(एम0एल0ए0)/2017 टी0सी0-। दिनांक 07.01.2022
TS Amount (lakhs) : 498.41 Lacs
Financial Detail
Sanction Cost : 498.41 Lacs
Resanction Cost : 498.41 Lacs
Exp. Upto Last Fy : 437.71 Lacs
For CFY 2024-2025
Remaining : 60.70 Lacs
Demand : 60.70 Lacs
Allotment : 41.73 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 437.71 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
2 years 4 months ago
07 Jan 2022
Tentative Completion date:
2 months 2 weeks ago
29 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इरेक्शन का कार्य प्रगति पर है। -- as on 15-May-2024
Physical Peramenters