Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 1 | 0 |
Span of Bridges [m] | 70 | 70 | 0.000 | 70 | 70.000 | 0.000 |
47W533 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 -470/।।।(2)/22-10(एम0एल0ए0)/2017 टी0सी0-। दिनांक 07.01.2022
TS Amount (lakhs) : 498.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
498.41
Resanction Cost :
498.41
Tentative Cost :
498.41
Exp. Upto Last Fy : 437.71
For CFY 2024-2025
Remaining : 60.70
Demand : 23.32
Allotment : 41.50
Exp in CFY : 31.70
Total Up to Date Exp : 469.41
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
2 days 5 hours ago
15 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 15-Jul-2024