Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
47W535 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : DM New Tehri Ltr No. 43/8-GO-09/2021-22 Dt. 05-07-2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 5.00 Lacs
Resanction Cost : 5.00 Lacs
Exp. Upto Last Fy : 0.25 Lacs
For CFY 2024-2025
Remaining : 4.75 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.25 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 10 months ago
05 Jul 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इस कार्य के समरेखण हेतु प्रारम्भिक सर्वेक्षण कर दिया गया है। समरेखण स्वीकृति हेतु कार्यालय को प्रेषित। -- as on 08-Jan-2024
Physical Peramenters