Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 4.500 | 0.000 |
47W543 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल सं0-49188 दिनंाक 28.03.2023
TS Amount (lakhs) : 166.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
166.87
Resanction Cost :
166.87
Tentative Cost :
166.87
Exp. Upto Last Fy : 20.58
For CFY 2024-2025
Remaining : 146.29
Demand : 133.99
Allotment : 25.00
Exp in CFY : 8.73
Total Up to Date Exp : 29.31
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 26 %
Sanction on :
1 year 3 months ago
28 Mar 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.30 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 10-Jul-2024
Physical Peramenters