Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 4.500 | 0.000 |
47W543 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल सं0-49188 दिनंाक 28.03.2023
TS Amount (lakhs) : 166.87 Lacs
Financial Detail
Sanction Cost : 166.87 Lacs
Resanction Cost : 166.87 Lacs
Exp. Upto Last Fy : 20.58 Lacs
For CFY 2024-2025
Remaining : 146.29 Lacs
Demand : 100.00 Lacs
Allotment : 25.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 20.58 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 1 month ago
28 Mar 2023
Tentative Completion date:
5 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1.00 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 15-May-2024
Physical Peramenters