Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
47W546 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल सं0-36456 दिनंाक 09.11.2022
TS Amount (lakhs) : 52.57 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
52.57
Resanction Cost :
52.57
Tentative Cost :
52.57
Exp. Upto Last Fy : 3.81
For CFY 2024-2025
Remaining : 48.76
Demand : 45.00
Allotment : 13.00
Exp in CFY : 11.64
Total Up to Date Exp : 15.45
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 34 %
Sanction on :
1 year 8 months ago
09 Nov 2022
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.500 कि0मी0 लम्बाई में पहाड़ कटान कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 10-Jun-2024
Physical Peramenters