Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
47W546 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई-फाईल सं0-36456 दिनंाक 09.11.2022
TS Amount (lakhs) : 52.57 Lacs
Financial Detail
Sanction Cost : 52.57 Lacs
Resanction Cost : 52.57 Lacs
Exp. Upto Last Fy : 3.81 Lacs
For CFY 2024-2025
Remaining : 48.76 Lacs
Demand : 45.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 3.81 Lacs
none
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 6 months ago
09 Nov 2022
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित किये जा चुके हैं कार्य प्रारम्भ की कार्यवाही की जा रही है। -- as on 13-Feb-2024
Physical Peramenters