Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.8 | 1.8 | 0.000 | 1.8 | 1.800 | 0.000 |
47W548 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-39499 Dt- 31-03-2023
TS Amount (lakhs) : 66.78 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
66.78
Resanction Cost :
66.78
Tentative Cost :
66.78
Exp. Upto Last Fy : 5.44
For CFY 2024-2025
Remaining : 61.34
Demand : 60.00
Allotment : 1.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.43
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.600 मीटर में पहाड़ कटान कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 09-Jul-2024
Physical Peramenters