Length of Road [Km] | 2 | 2 | 0.000 | 2 | 0.000 | 0.000 |
47W550 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Ltr No. 895/07 Yata-PMGSY-ni.-III Dt. 16.05.2023
TS Amount (lakhs) : 35.81 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
35.81
Resanction Cost :
35.81
Tentative Cost :
35.81
Exp. Upto Last Fy : 15.26
For CFY 2024-2025
Remaining : 20.55
Demand : 20.55
Allotment : 5.00
Exp in CFY : 3.83
Total Up to Date Exp : 19.09
Work completed
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
2 months 2 weeks ago
30 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 26-Jun-2024