Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.2 | 6.2 | 0.000 | 6.2 | 6.200 | 0.000 |
47W551 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Ltr No. 895/07 Yata-PMGSY-ni.-III Dt. 16.05.2023
TS Amount (lakhs) : 83.75 Lacs
Financial Detail
Sanction Cost : 83.75 Lacs
Resanction Cost : 83.75 Lacs
Exp. Upto Last Fy : 10.49 Lacs
For CFY 2024-2025
Remaining : 73.26 Lacs
Demand : 73.26 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 10.49 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रारम्भ किया जा चुका है। -- as on 21-Feb-2024
Physical Peramenters