Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
47W552 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Ltr No. 895/07 Yata-PMGSY-ni.-III Dt. 16.05.2023
TS Amount (lakhs) : 73.92 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
73.92
Resanction Cost :
73.92
Tentative Cost :
73.92
Exp. Upto Last Fy : 31.02
For CFY 2024-2025
Remaining : 42.90
Demand : 42.90
Allotment : 8.48
Exp in CFY : 0.00
Total Up to Date Exp : 31.02
Work completed
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
5 months 3 weeks ago
25 Jan 2024
Actual Completion Date:
5 months 3 weeks ago
25 Jan 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 26-Jun-2024