Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 14.68 | 14.68 | 0.000 | 14.68 | 14.680 | 0.000 |
47W555 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Ltr No. 895/07 Yata-PMGSY-ni.-III Dt. 16.05.2023
TS Amount (lakhs) : 253.07 Lacs
Financial Detail
Sanction Cost : 253.07 Lacs
Resanction Cost : 253.07 Lacs
Exp. Upto Last Fy : 89.96 Lacs
For CFY 2024-2025
Remaining : 163.11 Lacs
Demand : 163.11 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 89.96 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
1 year 3 days ago
16 May 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रारम्भ किया जा चुका है। -- as on 21-Feb-2024
Physical Peramenters