Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 110 | 110 | 0.000 | 110 | 0.000 | 0.000 |
47W560 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-39499 Dt- 09-03-2023
TS Amount (lakhs) : 22 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
22.00
Resanction Cost :
22.00
Tentative Cost :
22.00
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 22.00
Demand : 2.00
Allotment : 4.50
Exp in CFY : 4.46
Total Up to Date Exp : 4.46
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
1 year 4 months ago
09 Mar 2023
Tentative Completion date:
1 year 5 months from now
31 Dec 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0पी0आर0 गठन की कार्यवाही की जा रही है। -- as on 15-Jul-2024
Physical Peramenters