Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
47W565 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : DM New Tehri Ltr No. 17/8-GO-09/2023-24 Dt. 01-07-2023
TS Amount (lakhs) : 8 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
8.00
Resanction Cost :
8.00
Tentative Cost :
8.00
Exp. Upto Last Fy : 6.69
For CFY 2024-2025
Remaining : 1.31
Demand : 1.31
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 6.69
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 2 weeks ago
01 Jul 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। -- as on 08-Jan-2024
Physical Peramenters