Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.5 | 5.5 | 0.000 | 5.5 | 5.500 | 0.000 |
47W574 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-48456 Dt- 31-07-2023
TS Amount (lakhs) : 92.22 Lacs
Financial Detail
Sanction Cost : 92.22 Lacs
Resanction Cost : 92.22 Lacs
Exp. Upto Last Fy : 19.95 Lacs
For CFY 2024-2025
Remaining : 72.27 Lacs
Demand : 72.27 Lacs
Allotment : 30.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 19.95 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 25 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
2 months 3 weeks ago
25 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रारम्भ किया जा चुका है। -- as on 21-Feb-2024
Physical Peramenters