Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 0.000 | 0.000 |
47W575 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-48456 Dt- 31-07-2023
TS Amount (lakhs) : 50.83 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
50.83
Resanction Cost :
50.83
Tentative Cost :
50.83
Exp. Upto Last Fy : 47.02
For CFY 2024-2025
Remaining : 3.81
Demand : 3.81
Allotment : 3.81
Exp in CFY : 5.46
Total Up to Date Exp : 52.48
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
3 months 1 week ago
10 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 26-Jun-2024