Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.75 | 8.75 | 0.000 | 8.75 | 0.000 | 0.000 |
47W577 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-48456 Dt- 31-07-2023
TS Amount (lakhs) : 146 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
146.00
Resanction Cost :
146.00
Tentative Cost :
146.00
Exp. Upto Last Fy : 113.27
For CFY 2024-2025
Remaining : 32.73
Demand : 32.73
Allotment : 20.00
Exp in CFY : 12.32
Total Up to Date Exp : 125.58
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
4 months 3 weeks ago
26 Feb 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 26-Jun-2024
Physical Peramenters