Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9 | 9 | 0 |
47W578 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-48456 Dt- 31-07-2023
TS Amount (lakhs) : 122.92 Lacs
Financial Detail
Sanction Cost : 122.92 Lacs
Resanction Cost : 122.92 Lacs
Exp. Upto Last Fy : 106.68 Lacs
For CFY 2024-2025
Remaining : 16.24 Lacs
Demand : 16.24 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 106.68 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष । -- as on 21-Feb-2024