Work Profile Report [47W591]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-File-39499 Dt- 02-08-2023
TS Amount (lakhs) : 181.26 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
181.26
Resanction Cost :
181.26
Tentative Cost :
181.26
Exp. Upto Last Fy :
0.76
For CFY 2024-2025
Remaining :
180.50
Demand :
150.00
Allotment :
55.00
Exp in CFY :
52.90
Total Up to Date Exp :
53.66
Construction Started
Sanction on : 1 year 4 months ago
02 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
50 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर है। -- as on 24-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand