Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
47W598 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Ltr No. 1550/01 Niyo-02(SDRF)/2023 Dt. 22.12.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
14.45
Resanction Cost :
14.45
Tentative Cost :
14.45
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 14.45
Demand : 14.45
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 3 weeks ago
22 Dec 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य का आगणन प्राविधिक स्वीकृति हेतु वृत्तीय कार्यालय को प्रेषित। निविदा आमंत्रण की कार्यवाही की जा रही है। -- as on 11-Jan-2024
Physical Peramenters