Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8.7 | 8.7 | 0.000 | 8.7 | 8.700 | 0.000 |
47W600 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-48456 Dt- 30-01-2024
TS Amount (lakhs) : 131.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
131.84
Resanction Cost :
131.84
Tentative Cost :
131.84
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 131.84
Demand : 131.84
Allotment : 45.00
Exp in CFY : 42.91
Total Up to Date Exp : 42.91
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
3 weeks 2 days ago
24 Jun 2024
Actual Completion Date:
3 weeks 2 days ago
24 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 27-Jun-2024
Physical Peramenters