Work Profile Report [47W601]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E-File-48456 Dt- 30-01-2024
TS Amount (lakhs) : 135.19 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
135.19
Resanction Cost :
135.19
Tentative Cost :
135.19
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
135.19
Demand :
135.19
Allotment :
130.00
Exp in CFY :
126.13
Total Up to Date Exp :
126.13
Work completed
Sanction on : 9 months 3 weeks ago
30 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 4 months 4 weeks ago
24 Jun 2024
Actual Completion Date : 4 months 4 weeks ago
24 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 29-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: