Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.98 | 7.98 | 0.000 | 7.98 | 7.980 | 0.000 |
47W601 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E-File-48456 Dt- 30-01-2024
TS Amount (lakhs) : 135.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
135.19
Resanction Cost :
135.19
Tentative Cost :
135.19
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 135.19
Demand : 135.19
Allotment : 105.78
Exp in CFY : 105.78
Total Up to Date Exp : 105.78
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
3 weeks 2 days ago
24 Jun 2024
Actual Completion Date:
3 weeks 2 days ago
24 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 29-Jun-2024
Physical Peramenters