Work Profile Report [47W602]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E-File-36456/10 Dt- 29-01-2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
6.75
Resanction Cost :
6.75
Tentative Cost :
6.75
Exp. Upto Last Fy :
0.25
For CFY 2025-2026
Remaining :
6.50
Demand :
4.50
Allotment :
2.11
Exp in CFY :
2.11
Total Up to Date Exp :
2.36
Alignment Approved
Sanction on : 1 year 10 months ago
29 Jan 2024
Physical Progress:
At start of FY 2025-2026 :
40 %
Up to Date :
40 %
Tentative Completion date on : 5 months 2 weeks ago
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
स्वीकृत समरेखण पर ग्रामीणों द्वारा विवाद किया जा रहा है। जिसके कारण सहमति नहीं बन पा रही है। -- as on 09-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: