Work Profile Report [47W611]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-File-39205 Dt- 12-03-2024
TS Amount (lakhs) : 175.74 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
175.74
Resanction Cost :
175.74
Tentative Cost :
175.74
Exp. Upto Last Fy :
137.04
For CFY 2025-2026
Remaining :
38.70
Demand :
38.70
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
137.04
Construction Started
Sanction on : 1 year 3 weeks ago
12 Mar 2024
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
90 %
Tentative Completion date on : 6 days 50 minutes ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
4.90 कि0मी0 लम्बाई में पहाड़ कटान का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 25-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: