Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.94 | 0 | 1.940 | -1.94 | 0.000 | 0.000 |
48W27 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 847/(1)/।।।(2)/20-46(सामान्य)/2013 टी0सी0। दिनांक 21.05.2020
TS Amount (lakhs) : 364.98 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
364.98
Resanction Cost :
364.98
Tentative Cost :
364.98
Exp. Upto Last Fy : 327.00
For CFY 2024-2025
Remaining : 37.98
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 327.00
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 1 month ago
21 May 2020
Tentative Completion date:
Yet To Decide
Actual Completion Date:
4 years 2 months ago
01 May 2020
Remark
Bottelneck: no issue
निर्माण कार्य पूर्ण । तीन वर्षीय अनुरक्षण कार्य पूर्ण। । -- as on 25-May-2024
Physical Peramenters