Work Profile Report [49W130]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0 3233/।।।(2)/ 14-04(प्रा0आ0) /2014 दिनांक 26.05.2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.10
Resanction Cost :
47.10
Tentative Cost :
47.10
Exp. Upto Last Fy :
0.17
For CFY 2025-2026
Remaining :
46.93
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.17
Survey work done
Sanction on : 11 years 1 month ago
26 May 2014
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
1 %
Tentative Completion date on : 8 months 3 weeks from now
31 Mar 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
सरेखन विवाद। पुनः सहमती बनाने का प्रयास किया जा रहा है -- as on 25-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: