Work Profile Report [49W137]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 4665/।।र्।(2)/14-22(प्रा0आ0)/14 दि0 23.9.2014
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
36.38
Resanction Cost :
36.38
Tentative Cost :
36.38
Exp. Upto Last Fy :
4.34
For CFY 2025-2026
Remaining :
32.04
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
4.34
Alignment Approved
Sanction on : 11 years 3 months ago
23 Sep 2014
Physical Progress:
At start of FY 2025-2026 :
15 %
Up to Date :
15 %
Tentative Completion date on : 1 year 2 months from now
31 Mar 2027
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
संरेखण विवाद , जिसे सुलझाने का प्रयास किया जा रहा है | -- as on 22-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: