Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
49W205 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 सं0-1868/।।।(2)/16-19(प्रा0आ0)/2016 दिनाॅक-07.06.2016
TS Amount (lakhs) : 160.06 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
160.06
Resanction Cost :
160.06
Tentative Cost :
160.06
Exp. Upto Last Fy : 55.04
For CFY 2024-2025
Remaining : 105.02
Demand : 60.00
Allotment : 26.00
Exp in CFY : 0.00
Total Up to Date Exp : 55.04
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 1 month ago
07 Jun 2016
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्वों का भुगतान शेष I -- as on 31-Mar-2023
Physical Peramenters