Work Profile Report [49W22]
Tenders
Project Activities
alerts
Administrative Approval Detail : शा0स0 1960/111-/08-09(एम0एल0ए0)/07 दिनाॅक 26.06.2008
TS Amount (lakhs) : 398.91 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
490.60
Resanction Cost :
490.60
Tentative Cost :
490.60
Exp. Upto Last Fy :
427.41
For CFY 2024-2025
Remaining :
63.19
Demand :
63.19
Allotment :
60.00
Exp in CFY :
52.99
Total Up to Date Exp :
480.40
Work completed
Sanction on : 16 years 5 months ago
26 Jun 2008
Physical Progress:
At start of FY 2024-2025 :
90 %
Up to Date :
100 %
Tentative Completion date on : 3 months 6 days from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण , वित्तीय दायित्व शेष | -- as on 26-Nov-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: