Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 13 | 13 | 10.000 | 3 | 2.000 | 0.000 |
49W22 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 1960/111-/08-09(एम0एल0ए0)/07 दिनाॅक 26.06.2008
TS Amount (lakhs) : 398.91 Lacs
Financial Detail
Sanction Cost : 490.60 Lacs
Resanction Cost : 490.60 Lacs
Exp. Upto Last Fy : 427.41 Lacs
For CFY 2024-2025
Remaining : 63.19 Lacs
Demand : 40.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 427.41 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
15 years 10 months ago
26 Jun 2008
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
पहाड कटान का कार्य 13.00 कि0मी0 तक अधिंकाश रूप से करा लिया गया हैै। कतिपय स्थानों डिफेक्ट कटिंग का कार्य गतिमान है। 10.00 कि0मी0 में पार्ट -2 का कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 06-Jan-2024
Physical Peramenters