Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 13 | 13 | 10.000 | 3 | 2.000 | 0.000 |
49W22 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0स0 1960/111-/08-09(एम0एल0ए0)/07 दिनाॅक 26.06.2008
TS Amount (lakhs) : 398.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
490.60
Resanction Cost :
490.60
Tentative Cost :
490.60
Exp. Upto Last Fy : 427.41
For CFY 2024-2025
Remaining : 63.19
Demand : 40.00
Allotment : 28.00
Exp in CFY : 27.91
Total Up to Date Exp : 455.31
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
16 years 3 weeks ago
26 Jun 2008
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
मुख्य अभियन्ता महोदय लो0नि0वि0, पौडी के द्वारा दिनांक 17.09.2023 को कार्यस्थल का निरीक्षण किया गया व पत्रांक 387/08नि0टि0/2023 दिनंाक 19.09.2023 के द्वारा दिये गये निर्देशों के क्रम मंे पहाड कटान के दो अनुबन्धों कि0मी0 14.000 से 14.500 तक ठेकेदार श्री सुभाष सिंह व कि0मी0 15.000 से 15.500 तक ठेकेदार श्री मालचन्द पंवार का अन्तिमीकरण करते हुये दोनों ठेकेदारों को काली सूची में डाला गया व पुनः निविदा आंमत्रित करते हुये डिफेक्ट कटिंग का कार्य कराया गया है। कि0मी0 19 में 6 मीटर स्पान की पुलिया का निर्माण कार्य पूर्ण करा लिया गया है व पुलिया से आवागमन हो रहा है। कि0मी0 18.500 से आगे पहाड कटान का कार्य जो पूर्व में किया गया था, वाशआउट हो गया था उसे मुख्य अभियन्ता महोदय द्वारा दिये गये निर्देशों के क्रम में पुनः निर्माण करा लिया गया है। मोटर मार्ग पर स्लिप मलवा हटाने का कार्य कराया जा रहा है।पहाड कटान का कार्य 13.00 कि0मी0 तक अधिंकाश रूप से करा लिया गया हैै। 10.00 कि0मी0 में पार्ट -2 का कार्य पूर्ण शेष कार्य प्रगति पर। -- as on 02-Jul-2024
Physical Peramenters