Work Profile Report [49W278]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0 सं0-53/।।।(2)/18-25/(प्रा0आ0)/2017 दिनाॅक 12.01.2018
TS Amount (lakhs) : 126.55 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
126.55
Resanction Cost :
126.55
Tentative Cost :
126.55
Exp. Upto Last Fy :
117.96
For CFY 2024-2025
Remaining :
8.59
Demand :
8.59
Allotment :
5.00
Exp in CFY :
4.57
Total Up to Date Exp :
122.53
Work completed
Sanction on : 6 years 11 months ago
12 Jan 2018
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 2 months 3 days from now
28 Feb 2025
Actual Completion Date : 3 years 11 months ago
31 Dec 2020
Physical Linear Components
Remark
कार्य पूर्ण, दायित्वों का भुगतान शेष। -- as on 31-Dec-2020
Assets :
Work not linked with IM
Bridges on The Basis of AI: