Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.85 | 0.85 | 0.850 | 0 | 0.000 | 0.000 |
49W281 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-504/।।।(2)/18-25(प्रा0आ0)/2017 दिनाॅक 07.02.2018
TS Amount (lakhs) : 66.04 Lacs
Financial Detail
Sanction Cost : 66.04 Lacs
Resanction Cost : 66.04 Lacs
Exp. Upto Last Fy : 25.19 Lacs
For CFY 2024-2025
Remaining : 40.85 Lacs
Demand : 20.00 Lacs
Allotment : 8.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 25.19 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
6 years 3 months ago
07 Feb 2018
Tentative Completion date:
1 year 1 month ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 07-Mar-2022
Physical Peramenters