Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
49W285 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-1101/।।।(2)/18-25(प्रा0आ0)/2017 टी0सी0 ।। दिनाॅक-09.03.2018
TS Amount (lakhs) : 76.24 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
76.24
Resanction Cost :
76.24
Tentative Cost :
76.24
Exp. Upto Last Fy : 64.45
For CFY 2024-2025
Remaining : 11.79
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 64.45
Work completed
Physical Progress:
At start of FY 2024-2025 : 95 %
Up to Date : 100 %
Sanction on :
6 years 4 months ago
09 Mar 2018
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण,दायित्वो का भुगतान शेष । -- as on 31-Jul-2020
Physical Peramenters