Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10.5 | 10.5 | 7.000 | 3.5 | 3.500 | 3.000 |
49W320 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1065/।।।(2)/19-25(प्रा0आ0)/2017 टी0सी0 दि0 25.02.2019 दिनाॅक 21.01.2020 द्वारा नाबार्ड में स्वीकृत,पी0आईसी0 नं0-पी0202021-30
TS Amount (lakhs) : 655.64 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
655.64
Resanction Cost :
655.64
Tentative Cost :
655.64
Exp. Upto Last Fy : 459.08
For CFY 2024-2025
Remaining : 196.56
Demand : 196.56
Allotment : 12.97
Exp in CFY : 0.00
Total Up to Date Exp : 459.08
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 85 %
Sanction on :
5 years 4 months ago
25 Feb 2019
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
नव निर्माण का कार्य 10.00 कि0मी0 तक अधिंकाश रूप से पूर्ण करा लिया गया हैै। मोटर मार्ग में 10 मीटर स्पान 01 नं0 सेतु, 15 मीटर स्पान 02 नं0 सेतु का निर्माण कार्य पूर्ण करा लिया गया है। कार्य को पूर्ण करने की लक्षित तिथि 30.06.2024 है, परन्तु 02 स्थानों पर मोटर मार्ग वाश आउट होने के कारण कार्य में विलम्ब हुआ है, मोटर मार्ग में अवशेष 500 मीटर का पहाड कटान का कार्य गतिमान है, अवशेष कार्य को दिनांक 31.07.2024 तक अधिक संसाधन लगाते हुये पूर्ण करा लिया जायेगा।
ग्रामीणों द्वारा मार्ग निर्माण में 02.12.2023 से 29.02.2023 तक विवाद किया जा था। वर्तमान मे विवाद सुलझा दिया गया है तथा कार्य प्रगति पर है।
-- as on 02-Jul-2024
Physical Peramenters