Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10.5 | 10.5 | 7.000 | 3.5 | 3.500 | 0.000 |
49W320 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1065/।।।(2)/19-25(प्रा0आ0)/2017 टी0सी0 दि0 25.02.2019 दिनाॅक 21.01.2020 द्वारा नाबार्ड में स्वीकृत,पी0आईसी0 नं0-पी0202021-30
TS Amount (lakhs) : 655.64 Lacs
Financial Detail
Sanction Cost : 655.64 Lacs
Resanction Cost : 655.64 Lacs
Exp. Upto Last Fy : 459.08 Lacs
For CFY 2024-2025
Remaining : 196.56 Lacs
Demand : 131.02 Lacs
Allotment : 12.97 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 459.08 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
5 years 2 months ago
25 Feb 2019
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड कटान का कार्य 10.00 कि0मी0 तक अधिंकाश रूप से करा लिया गया हैै। कतिपय स्थानों डिफेक्ट कटिंग का कार्य गतिमान है। 7.00 कि0मी0 में पार्ट -2 का कार्य पूर्ण शेष कार्य प्रगति पर एवं 10 मीटर आर0सी0सी0 पुल का निर्माण कार्य पूर्ण एवं कि0मी0 29 में 15 मीटर आर0सी0सी0 पुल का बीम/स्लेब के शटरिंग का कार्य प्रगति में तथा कि0मी0 30 में 15 मीटर आर0सी0सी0 पुल के राफ्ट फाॅउडेशन व एबटमेंट का कार्य पूर्ण शेष कार्य प्रगति पर है। कार्य दि॰ 30.06.2024 तक पूर्ण कर लिया जायेगा।
ग्रामीणों द्वारा मार्ग निर्माण में 02.12.2023 से 29.02.2023 तक विवाद किया जा था। वर्तमान मे विवाद सुलझा दिया गया है तथा कार्य प्रगति पर है।
-- as on 06-Mar-2024
Physical Peramenters