Work Profile Report [49W428]
Tenders
Project Activities
alerts
Administrative Approval Detail : शा0 सं0 1589/।।।(2)/20-06 (मु0मं0घो0)/2015, दिनांक 26.08.2020।
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
163.12
Resanction Cost :
129.12
Tentative Cost :
129.12
Exp. Upto Last Fy :
47.16
For CFY 2024-2025
Remaining :
81.96
Demand :
15.00
Allotment :
0.00
Exp in CFY :
0.33
Total Up to Date Exp :
47.49
Work completed
Sanction on : 4 years 2 months ago
26 Aug 2020
Physical Progress:
At start of FY 2024-2025 :
65 %
Up to Date :
100 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण, दायित्व शेष | -- as on 05-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: