Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 61.5 | 61.5 | 56.000 | 5.5 | 5.500 | 0.000 |
No of Bridges | 1 | 1 | 1 | 0 | 0 | 0 |
Span of Bridges [m] | 12 | 12 | 12.000 | 0 | 0.000 | 0.000 |
49W446 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 1185/।।।(3)/2021-16(सी0आर0आई0एफ)/2021 दिनांक 27.10.2021
TS Amount (lakhs) : 5534.86 Lacs
Financial Detail
Sanction Cost : 5,534.86 Lacs
Resanction Cost : 5,914.76 Lacs
Exp. Upto Last Fy : 5,534.86 Lacs
For CFY 2024-2025
Remaining : 379.90 Lacs
Demand : 250.00 Lacs
Allotment : 100.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 5,534.86 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 97 %
Up to Date : 97 %
Sanction on :
2 years 6 months ago
27 Oct 2021
Tentative Completion date:
4 days 2 hours ago
15 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
61 किमी0 डीबीएम तथा 56.00 किमी बीसी का कार्य पूर्ण शेष कार्य प्रगति पर तथा 12मी0 आर0सी0सी0 सेतु के स्लैब कास्टिंग का कार्य पूर्ण शेष कार्य प्रगति पर है। -- as on 01-Dec-2023
Physical Peramenters