Work Profile Report [49W476]
Tenders
Project Activities
alerts
Administrative Approval Detail : शा0सं0 (ई-पत्रावली सं0) 28320 दिनाॅक-03.08.2022
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : Bridges State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
3.60
Resanction Cost :
3.60
Tentative Cost :
3.60
Exp. Upto Last Fy :
3.10
For CFY 2025-2026
Remaining :
0.50
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
3.10
Phase1 DPR Submitted
Sanction on : 2 years 11 months ago
03 Aug 2022
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 months ago
31 Mar 2024
Actual Completion Date : 1 year 3 months ago
31 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण, दायित्वों का भुगतान शेष। -- as on 02-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: