Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.825 | 1.825 | 0.000 | 1.825 | 1.825 | 0.000 |
49W494 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई पत्रावली संख्या- 28320/दिनांक 09.11.2022
TS Amount (lakhs) : 142.83 Lacs
Financial Detail
Sanction Cost : 142.83 Lacs
Resanction Cost : 142.83 Lacs
Exp. Upto Last Fy : 98.66 Lacs
For CFY 2024-2025
Remaining : 44.17 Lacs
Demand : 40.86 Lacs
Allotment : 10.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 98.66 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
1 year 6 months ago
09 Nov 2022
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0 1,जी-2 व जी-3 का कार्य पूर्ण शेष कार्य प्रगति पर है। -- as on 07-Mar-2024
Physical Peramenters