Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 3.000 | 0.000 |
49W562 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : उत्तराखण्ड शासन की ई-पत्रावली संख्या 47979 दिनांक 29.08.2023।
TS Amount (lakhs) : 483.31 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
483.31
Resanction Cost :
483.31
Tentative Cost :
483.31
Exp. Upto Last Fy : 45.20
For CFY 2024-2025
Remaining : 438.11
Demand : 42.00
Allotment : 35.00
Exp in CFY : 35.00
Total Up to Date Exp : 80.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 14 %
Up to Date : 41 %
Sanction on :
10 months 2 weeks ago
29 Aug 2023
Tentative Completion date:
5 months 4 weeks from now
17 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
जी0 1 का कार्य 5 किमी0 ,जी0 2 का कार्य 4 किमी0 व जी0 3 का कार्य 3.00 किमी0 तक पूर्ण शेष कार्य प्रगति पर है। -- as on 02-Jul-2024
Physical Peramenters