Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 20.18 | 20.18 | 20.18 | 0 |
49W576 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0 का पत्रांक-272/ ।।।(2)2024-01(प्रा0आ0)/2023 दिं0 31.01.2024
TS Amount (lakhs) : 344.68 Lacs
Financial Detail
Sanction Cost : 344.68 Lacs
Resanction Cost : 344.68 Lacs
Exp. Upto Last Fy : 99.57 Lacs
For CFY 2024-2025
Remaining : 245.11 Lacs
Demand : 245.11 Lacs
Allotment : 80.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 99.57 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
3 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 18-Mar-2024
Physical Peramenters