Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 64.28 | 64.28 | 0.000 | 64.28 | 25.000 | 0.000 |
49W608 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0 256/III(3)/2024-01(CRIF)2022 दिनांक 29.02.2024 & 322/III(3)/2024-14(CRIF)2024 दिनांक 16.03.2024 & 462/III(3)/2024-14(CRIF)2024 दिनांक 02.05.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
2143.97
Resanction Cost :
2143.97
Tentative Cost :
2143.97
Exp. Upto Last Fy : 200.00
For CFY 2024-2025
Remaining : 1,943.97
Demand : 650.00
Allotment : 200.00
Exp in CFY : 79.78
Total Up to Date Exp : 279.78
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 23 %
Sanction on :
4 months 2 weeks ago
29 Feb 2024
Tentative Completion date:
10 months 3 weeks from now
11 Jun 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
वर्तमान में मोटर मार्ग परअंधे मोड़ो के सुधार हेतु 52 किमी के सापेक्ष 37 किमी का कार्य पूर्ण कराया जा चुका है व बी0सी0 का कार्य 5.00 किमी0 तक पूर्ण एवं मोटर मार्ग पर क्राॅस ड्रैनेज का कार्य तथा शेष शेष कार्य प्रगति पर है। -- as on 03-Jul-2024
Physical Peramenters