Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 9 | 9 | 4.500 | 4.5 | 0.000 | 0.000 |
4W49 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं.829/ प्प्प्-2/ 06 -62 (प्रा.आ.)/05 टी.सी.-1 दि.28.3.06
TS Amount (lakhs) : 284.97 Lacs
Financial Detail
Sanction Cost : 125.10 Lacs
Resanction Cost : 159.87 Lacs
Exp. Upto Last Fy : 128.94 Lacs
For CFY 2024-2025
Remaining : 30.93 Lacs
Demand : 20.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 128.94 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
15 years 1 month ago
28 Mar 2009
Tentative Completion date:
3 years 1 month ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
fदनांक 12.6.19 को fवfधवत स्वीकृfत प्राप्त। मार्ग में पड़ने वाले वृक्षों के छपान के पातन हेतु इस कार्यालय के पत्रांक 1569/18सी. fदनांक 10.6.19 द्वारा प्रभागीय वनाfधकारी, अल्मोड़ा को पत्र fलखा गया है। 6.00 किमी. पहाड़ कटान एवं 4.50 किमी. में पार्ट-2 का कार्य पूर्ण। मार्ग के किमी. 7 चैनेज 6.00 से 6.835 के बीच वृक्षों का पातन न होने के कारण पहाड़ कटान का कार्य अवरूद्व है। वृक्षों के पातन हेतु प्रभागीय वनाधिकारी, अल्मोड़ा को इस काया्रलय के पत्र सं. 2608/18सी. दिनांक 6.9.2022 तथा पत्रांक 3173/18सी. दिनांक 22.11.2023 द्वारा पत्र प्रेषित। वृक्षों के पातन के पश्चात अवशेष पहाड़ कटान का कार्य प्रगति पर है। ( पुनरीक्षित स्वीकृति शासनादेश संख्या 6177/111(2)/2021-48(एम.एल.ए.)/2017 टी.सी.11 दिनांक 22.12.2021 द्वारा लम्बाई 6.825 लागत रू. 159.87 लाख की प्राप्त है।) -- as on 05-Feb-2024
Physical Peramenters