Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
Span of Bridges [m] | 6 | 6 | 6.000 | 0 | 0.000 | 0.000 |
4W545 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं. 275(ए)/111(2) /19-48(एम.एल.ए.)/2017 टी.सी.-1 दिनांक 22.1.2019
TS Amount (lakhs) : 330.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
330.85
Resanction Cost :
330.85
Tentative Cost :
330.85
Exp. Upto Last Fy : 293.17
For CFY 2024-2025
Remaining : 37.68
Demand : 30.00
Allotment : 40.00
Exp in CFY : 0.00
Total Up to Date Exp : 293.17
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
5 years 5 months ago
22 Jan 2019
Tentative Completion date:
1 month 2 weeks ago
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 23.06.2020 एवं कार्य पूर्ण करने की तिथि 22.11.2021है। -- as on 04-Jul-2024
Physical Peramenters