Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5.000 | 0 | 0.000 | 0.000 |
Span of Bridges [m] | 6 | 6 | 6.000 | 0 | 0.000 | 0.000 |
4W545 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं. 275(ए)/111(2) /19-48(एम.एल.ए.)/2017 टी.सी.-1 दिनांक 22.1.2019
TS Amount (lakhs) : 330.85 Lacs
Financial Detail
Sanction Cost : 330.85 Lacs
Resanction Cost : 330.85 Lacs
Exp. Upto Last Fy : 293.17 Lacs
For CFY 2024-2025
Remaining : 37.68 Lacs
Demand : 30.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 293.17 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 90 %
Sanction on :
5 years 3 months ago
22 Jan 2019
Tentative Completion date:
1 week 4 days from now
31 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
5किमी. लम्बाई के सापेक्ष पहाड़ कटान का कार्य पूर्ण। किमी. 1 व 4 में जल संस्थान की पाईप लाईन मार्ग के समरेखन में आने के कारण कार्य बाधित रहा। जल संस्थान द्वारा पाईप लाईन मार्ग के समरेखन से हटा दी गयी है। कार्य प्रगति पर हेै। दिनांक 31.05.2024 तक कार्य पूर्ण कर लिया जायेगा।अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 23.06.2020 एवं कार्य पूर्ण करने की तिथि 22.11.2021है। -- as on 10-Apr-2024
Physical Peramenters