Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
4W619 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं. 5़959/111(2)/2021-48(एम.एल.ए.)/2017 दिनांक 06.12.2021
TS Amount (lakhs) : 207.17 Lacs
Financial Detail
Sanction Cost : 207.17 Lacs
Resanction Cost : 207.17 Lacs
Exp. Upto Last Fy : 95.26 Lacs
For CFY 2024-2025
Remaining : 111.91 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 95.26 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
2 years 5 months ago
06 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
3 किमी. में सोलिंग कोट, इन्टर कोट एवं टाॅप कोट का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 06-Mar-2024
Physical Peramenters