Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.15 | 2.15 | 0.000 | 2.15 | 2.150 | 1.000 |
4W649 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल नं014293 दिनांक16.3.2023
TS Amount (lakhs) : 102.67 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
102.67
Resanction Cost :
102.67
Tentative Cost :
102.67
Exp. Upto Last Fy : 59.63
For CFY 2024-2025
Remaining : 43.04
Demand : 43.00
Allotment : 50.00
Exp in CFY : 0.00
Total Up to Date Exp : 59.63
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
1 year 4 months ago
16 Mar 2023
Tentative Completion date:
1 week 6 days from now
31 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 23.09.2023 एवं कार्य पूर्ण करने की तिथि 12.09.2024 है। -- as on 04-Jul-2024
Physical Peramenters