Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 7 | 3 | 3 | 0 |
4W650 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल नं049297
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
26.68
Resanction Cost :
22.16
Tentative Cost :
22.16
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 22.06
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 3 months ago
20 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। 46 मी0 स्पान का सेतु पूर्व में ए क्लास लोडिंग का निर्मित है। -- as on 27-Jun-2024
Physical Peramenters