Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
4W653 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No.- 49618 Date 29-3-2023
TS Amount (lakhs) : 271.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
271.87
Resanction Cost :
271.87
Tentative Cost :
271.87
Exp. Upto Last Fy : 74.22
For CFY 2024-2025
Remaining : 197.65
Demand : 150.00
Allotment : 100.00
Exp in CFY : 22.72
Total Up to Date Exp : 96.94
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 3 months ago
23 Mar 2023
Tentative Completion date:
8 months 18 hours from now
18 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 19.12.2023 एवं कार्य समाप्ति की तिथि 18.03.2025 है। 5 किमी. में सोलिंग,इन्टर का कार्य पूर्ण। शेष कार्य प्रगति पर है। -- as on 04-Jul-2024
Physical Peramenters